Timeline of 10.5 upgrade implementation.

In case you missed it, OSP is working with Huron to upgrade ResearchUVA (RUVA) to version 10.5. See below for the implementation timeline, running from now to the beginning of August. 

Plotting a Route to 10.5

OSP and the OVPR Info Team have been deep in preparations for this significant RUVA upgrade. Now that project pre-work is wrapping up, we are ready to start our trek to RUVA's Huron 10.5 go-live. The plan begins with testing in the Preview environment this months and culminates with stabilization and the end of Huron's support. 

Timeline and Tasks

TimeTask
April 21UVA testing begins in the Preview environment.
Mid-May

OSP, Submitting Schools, and Research Administrators begin User Acceptance Testing (UAT).

If you would like to participate in UAT, email MaryBeth Spaulding (mas7zt@virginia.edu). 

June 13Testing wraps up.
July 25The upgrade begins after COB.
July 28(Anticipated) RUVA is back online.
August 8Stabilization support from Huron ends. 

Keep in Mind

This is a high-level plan that may change as the unexpected pops up. OSP is committed to keeping you—our colleagues—in the loop of any possible changes or delays. 